Day 1 of 3 · 6 hours · Level 1 Beginner

Accounting, cash management and budget control

Learning objectives for today
  • Justify and code every expense.
  • Manage cash and bank accounts.
  • Monitor the budget monthly.

1Supporting documents first and foremost

Every expense must be backed by original supporting documents: approved request, purchase order, goods received note, invoice, proof of payment. No document, no eligible expense.

  • Documents are numbered and stamped “paid” with the project reference to prevent double funding.
  • Each entry carries a budget code (budget line) and a cost code (project, donor, location): this is what makes it possible to produce reports by donor.
  • Entries are recorded in accounting software or a structured spreadsheet (cash book, bank book), as transactions occur.

2Cash and bank

  • Cash ceiling: a maximum amount of cash held in the office, set by the policy and the insurance; above that, payments are made by bank or mobile money.
  • Regular cash counts (for example every week and at each month end) by two people, with a signed cash count report.
  • Monthly bank reconciliation: the bank statement balance compared with the book balance, with every difference explained.
  • Dual signatures on bank payments above a threshold.
  • Advances (to staff or for field trips): authorised, recorded and justified within a set deadline.
  • Cash flow forecast: anticipate needs so as to request donor instalments on time.

3Budget monitoring

Every month, a budget versus actual report (BvA) compares, line by line, the budget, the month's expenditure, the cumulative total, the burn rate and the balance.

  • Compare the burn rate with the time elapsed: in month 6 of 12, a line at 90% or 10% warrants analysis.
  • Discuss the report with the project manager: activity delays, changing prices, reallocation needs.
  • Respect the flexibility provided for in the contract (for example a percentage between lines); beyond that, request the donor's written approval.
  • Check eligibility: the expense is budgeted, necessary, reasonable, within the project period, justified and compliant with the donor's rules.
In-depth course

Detailed methods, a complete worked example, tools, common mistakes and interview questions.

4The expenditure cycle step by step: from expressed need to filed voucher

Most costs disallowed at audit do not stem from fraud but from a poorly managed expenditure cycle: a request approved after the purchase, a missing goods received note, an invoice charged to the wrong budget line, a payment made before the contract start date. The expenditure cycle (procure-to-pay) is the backbone of compliance. Each step has an owner, a document and a control. If a step is missing, the expenditure becomes vulnerable, even if it is genuine and useful.

The eight steps of the standard cycle

StepOwnerDocument producedKey control
1. Expression of needProject manager or activity leadDated purchase or payment request, with proposed project code and budget lineThe need is foreseen in the activity plan and the budget
2. Budget checkFinance (finance officer or accountant)"Funds available" sign-off on the requestSufficient balance on the line; expenditure eligible under the contract
3. ApprovalHolder of the delegation of authority for that amountDated signatureApproval precedes commitment; the approver is not the requester
4. CommitmentLogistics (procurement)Quotations, bid analysis, purchase order or contractProcurement procedure followed according to thresholds
5. ReceiptA person other than the buyerGoods received note or certificate of service renderedQuantity and quality match the order
6. VerificationFinanceMatching of order, receipt and invoiceThe three documents agree (amount, quantity, supplier)
7. PaymentCashier or bank, on signed instructionCheque, bank transfer, signed receipt, proof of mobile money transferDual signature above the threshold; payment in the supplier's name, never to a third party
8. Recording and filingAccountantCoded entry, voucher stamped "paid", numbered and filedCorrect budget and cost-centre codes; voucher retrievable in under five minutes

Three-way matching (order, receipt, invoice) is the most effective and least costly control against overbilling and fictitious deliveries. If any one of the three documents is missing, verification is suspended, whatever urgency is claimed.

Coding: what makes the accounts readable by donor

A properly coded entry answers four questions: what type of expenditure (general ledger account), for which project and which donor (project code), against which line of the donor budget (budget code), and where (location or base code). An NGO managing three donors without reliable cost-centre coding cannot produce a defensible financial report, and ends up "reconstructing" charges at reporting time, something auditors spot immediately.

ElementExamplePurpose
General ledger account6061 FuelNature of the expenditure, for the organisation's financial statements
Project codeP24-ECHO-03Links the expenditure to a specific contract
Budget code3.2 Transport of inputsMatches the line in the budget approved by the donor
Location codeBAS-KOR (Koro base)Enables tracking by base and allocation of shared costs
Activity code (optional)A2.1 DistributionLinks cost to results (cost per beneficiary)

The correspondence table between the organisation's chart of accounts and each donor's budget lines (mapping) is prepared at the start of every contract, validated by the finance manager and shared with the staff who enter transactions. It prevents the same fuel purchase from being charged to "transport" by one base and to "running costs" by another.

Supporting documents required by type of expenditure

Type of expenditureMinimum supporting documentsPoint of attention
Purchase of goodsApproved request, quotations according to threshold, bid analysis, purchase order, delivery note and goods received note, original invoice, proof of paymentConsistent dates: the order cannot precede the request, and the invoice cannot precede delivery unless there is a contractual advance
SalariesEmployment contract, payslip, approved payroll, timesheet if the position is shared, proof of transfer, social security and tax returnsThe percentage charged to the project must match the time actually worked
Per diems and travelApproved travel authorisation (mission order), applicable rate scale, signed attendance list, mission reportNo per diem for a day on which meals are already provided, in line with the policy
Transfers to beneficiariesValidated list, proof of identity or code, proof of receipt (signature, thumbprint, mobile operator confirmation), reconciliation with the operator's reportLists are checked for duplicates before payment
Rental (office, vehicle)Signed contract, proof of ownership or of the landlord's mandate, rent receipts, inventory of conditionRent paid in advance beyond the project end date is not eligible
Transfer to a partnerPartnership agreement, funding request, proof of transfer, partner financial report with supporting documents or verificationThe transfer is not a final expenditure: only the expenditure justified by the partner is

Deadlines and rhythm

  • Recording of entries: no later than five working days after payment; for cash, the same day.
  • Clearance of staff advances: seven to fourteen days after return from mission, depending on the policy; no new advance until the previous one is cleared.
  • Sending supporting documents from bases to the country office: weekly in a stable context, at least monthly where access is difficult, with a transmittal slip and a scanned copy kept on site.
  • Retention: according to the most demanding contract. As an indication, the EU Financial Regulation generally requires five years after payment of the balance (three years for low-value grants), and the US federal regulations (2 CFR 200) three years from submission of the final financial report, extended where an audit or litigation is ongoing.

5Month-end closing: timetable, reconciliations and consistency checks

Month-end closing is the point at which accounting becomes reliable management information. A closing done late or without controls produces an incorrect budget versus actuals (BvA) report, and decisions taken on that basis are wrong too. In a well-run mission, the month's accounts are closed and sent to headquarters between the fifth and tenth working day of the following month.

Typical closing timetable

DayTaskOwner
Last day of the monthCash count at each base and at the country office, by two people, with a signed cash count reportCashier and a designated witness (not their direct line manager if that person also handles the cash)
D+1 to D+2Receipt of supporting documents from bases, follow-up of uncleared advancesFinance officer
D+2 to D+3Entry of the final transactions, receipt of bank statements and mobile money operator statementsAccountant
D+3 to D+4Bank and cash reconciliations; analysis of suspense accounts and advancesAccountant, reviewed by the finance manager
D+4 to D+5Review of coding (sample), shared cost allocation entries, exchange differencesFinance manager
D+5 to D+7Production of budget versus actuals reports by project; budget review meeting with project managersFinance manager and project managers
D+7 to D+10Submission to headquarters: trial balance, signed reconciliations, cash count reports, BvA reports with commentsFinance manager, signed off by the country director

The bank reconciliation, full method

The reconciliation explains the difference between the bank statement balance and the cash book (bank ledger) balance on the same date. Legitimate differences are of four types: cheques issued but not yet debited, deposits or transfers recorded in the accounts but not yet credited by the bank, bank charges and interest not yet recorded in the accounts, and transfers received by the bank but not yet recorded. Anything else is an error or an anomaly to be explained.

Reconciliation at 31 March (in US dollars)Amount
Balance per bank statement48,260.00
Less: cheque no. 1043 issued on 29 March, not yet presented (cement supplier)- 3,150.00
Less: cheque no. 1045 issued on 31 March, not yet presented (April rent)- 1,200.00
Add: cash deposit of 31 March lodged after the bank's closing time+ 500.00
Adjusted bank balance44,410.00
Balance per bank ledger44,455.00
Less: March bank charges not yet recorded- 45.00
Adjusted book balance44,410.00
Unexplained difference0.00

The reconciliation is prepared by the accountant, reviewed and signed by someone who has no access to payments, and accompanied by the original bank statement. Reconciling items must be followed up: a cheque outstanding for more than three months must be investigated (lost cheque, non-existent supplier, cheque to be cancelled and reissued), because this is a classic avenue for misappropriation.

A reconciliation "balanced" with a line labelled "difference to be analysed" or "miscellaneous" is not a reconciliation. A difference, even of 10 dollars, signals either a data entry error that will recur or a manipulation that will grow.

The cash count report

The count is done denomination by denomination, in the presence of the cashier, by an independent person. The report records: date and time, denominations and quantities, physical total, theoretical cash book balance, difference, explanation, and the signatures of both people. IOUs (outstanding advances backed by a signed document) are listed separately: they are not cash on hand, and their cumulative amount must be capped by the policy. A cash box that permanently holds IOUs for 40% of its balance is a cash box being used to lend money to staff.

Month-end consistency checks

  • Suspense accounts: unallocated amounts must be cleared at each closing or, failing that, justified line by line with a regularisation date.
  • Staff advances: ageing analysis (under 15 days, 15 to 30 days, over 30 days). Beyond 30 days, escalation to the director and, depending on the policy, deduction from salary after written agreement.
  • Salaries: the month's payroll agrees with the staff list validated by human resources; starters and leavers are documented.
  • Coding: review of a sample of entries (for example ten entries per project, selected among the largest plus a few at random) to check supporting documents, codes and dates.
  • Shared costs: the month's allocation key is calculated and applied according to the documented method.
  • Exchange: the rate applied is the one set by the policy and by each contract; exchange differences are recorded separately.

6Eligibility, direct costs and shared costs: applying donor rules

An expenditure can be genuine, documented and useful, and still ineligible. Eligibility is assessed against the signed contract and the donor's general rules, which take precedence over the organisation's internal policy where they are stricter. The basic principle is that the organisation always applies the more demanding rule of its own policy and the donor's.

Common eligibility criteria

Despite different wording, the major donors share a common set of criteria. The US federal regulations (2 CFR 200, Subpart E, "Cost Principles") refer to costs that are allowable (section 200.403), allocable (section 200.405) and reasonable (section 200.404). The European Union rules for humanitarian aid (ECHO's Framework Partnership Agreement and its annexes) require costs that are necessary for the action, provided for in the budget, incurred during the implementation period, identifiable and verifiable, recorded in the accounts, compliant with applicable tax and social legislation, reasonable and justified, and consistent with the principle of sound financial management.

CriterionQuestion to askExample of disallowance
Budgeted and necessaryIs the expenditure linked to a project activity and a budget line?Purchase of a second vehicle not in the budget, without donor approval
Within the periodDid the commitment and delivery take place between the start date and the end date?Invoice for a workshop dated ten days before the contract start, with no retroactivity clause
ReasonableWould a prudent buyer have paid this price in this context?Rice price 35% above the cluster's market price monitoring for the same week
AllocableDid the project benefit from the expenditure, and in what proportion?Director's salary charged 100% to one project although they manage five projects
Documented and recordedDo the supporting documents exist, and is the entry in the accounts?Expenditure reported but missing from the general ledger
Compliant with proceduresWere the procurement, recruitment and origin rule procedures followed?18,000-dollar purchase on a single quotation when the policy required three
No double fundingIs the same expenditure claimed from another donor?Same rent allocated 60% to one project and 60% to another

Direct costs, shared costs and indirect costs

  • Direct costs: they relate unambiguously to one project (distributed inputs, staff at 100%, dedicated vehicle).
  • Shared costs (or direct support costs): they benefit several projects in the same country (country office rent, electricity, country logistician, security). They can be charged directly to projects if an objective, documented, consistently applied and verifiable allocation method is used.
  • Indirect costs: headquarters overheads that cannot be attributed to a specific project. They are covered by a flat-rate percentage or a negotiated rate. For example, ECHO generally caps indirect costs at 7% of eligible direct costs; the US federal regulations allow a negotiated rate (NICRA) or, failing that, a de minimis rate (raised to 15% of modified total direct costs in the 2024 revision); several United Nations agencies and pooled funds apply a 7% rate for implementing partners. These rates must always be checked in the contract.

Methods for allocating shared costs

MethodBasis of calculationSuitable forLimitation
Pro rata to headcountNumber of staff (or full-time equivalents) per projectRent, supplies, internetMust be recalculated every month if headcount changes
Pro rata to direct costsEach project's share of the month's direct expenditureGeneral support costsPenalises projects with a large cash transfer component
Actual usageKilometres per project (logbook), hours (timesheets)Vehicles, generator, shared staffRequires rigorous and reviewed records
Pro rata to floor spaceSquare metres occupiedWarehousesPoorly suited if occupancy changes often

What the auditor checks in an allocation: a written method, approved before it is applied, applied every month in the same way to all projects, and whose percentages never add up to more than 100%. An allocation decided according to the budget remaining on each project is an opportunistic allocation and will be disallowed.

Staff and timesheets

Salaries are often the largest budget line and the leading source of disallowed costs. For any position charged to several projects, most donors expect a timesheet that reflects the time actually worked, signed by the employee and their supervisor, completed at least monthly. A fixed budget percentage applied for twelve months without timesheets is an estimate, not evidence. The US federal regulations (2 CFR 200.430) require charges for personnel to be based on records that accurately reflect the work performed; budget estimates are accepted only if they are adjusted after the fact to actuals.

Budget flexibility and amendments

Each contract sets a margin for transfers between lines or headings without prior approval. The US federal regulations (2 CFR 200.308), for example, require prior approval when cumulative transfers among direct cost categories exceed 10% of the total budget, above a certain award amount. ECHO contracts and those of United Nations agencies provide for their own margins, to be read in the special conditions. Three practical rules: calculate flexibility cumulatively over the life of the project, not month by month; never use flexibility to create a new line or an unbudgeted piece of equipment; request an amendment at least 30 to 60 days before it is needed, and never in the last month of the project.

7Worked example: the month 7 budget versus actuals and the reallocation request

Fictional context: the national NGO "Entraide Rive Sud" is implementing a 12-month project assisting displaced households in the fictional district of Malanga, funded by an institutional donor. The total budget is 419,440 dollars, of which 392,000 are direct costs and 27,440 indirect costs (7% of direct costs). The contract allows transfers between headings without an amendment up to 15% of the initial amount of the receiving heading, on simple written notification; beyond that, an amendment is required. We are at the month 7 closing, i.e. 58% of the time elapsed.

Step 1: the budget versus actuals table

HeadingBudgetCumulative at M7Burn rateVariance to time (58%)Signal
1. Staff150,00084,00056.0%- 2 pointsNormal
2. Distributions (kits and transfers)160,00062,40039.0%- 19 pointsTo be analysed
3. Transport and logistics38,00031,20082.1%+ 24 pointsAlert
4. Office and running costs24,00015,60065.0%+ 7 pointsTo be monitored
5. Equipment20,00019,40097.0%not applicableNormal (one-off purchase at project start)
Total direct costs392,000212,60054.2%- 4 points
6. Indirect costs (7%)27,44014,88254.2%
Total419,440227,48254.2%

First reading: the overall burn rate (54.2%) is close to the time elapsed, which could be falsely reassuring. The line-by-line analysis shows two opposite movements that offset each other. The burn rate compared with time elapsed is only a signal: it must always be checked against the activity schedule. Equipment is normally spent at the start of the project; distributions follow a schedule of cycles.

Step 2: understanding each variance with the project manager

  • Transport: the fuel price rose by 28% in month 3 (regional shortage), and the main road to two sites has been cut since month 5, forcing a 140-kilometre detour. Monthly average: 31,200 / 7 = 4,457 dollars. At the same rate, the end-of-project forecast is 4,457 × 12 = 53,486 dollars, an overspend of 15,486 dollars (40.8%).
  • Distributions: the second cycle was postponed by six weeks because of insecurity. Commitments for months 8 to 10 (signed orders and validated lists) amount to 90,000 dollars. Forecast: 62,400 + 90,000 = 152,400, a saving of 7,600 dollars, due to a lower kit price obtained through a framework agreement. The targets (2,400 households) remain achievable.
  • Staff: 12,000 dollars per month on average; a field assistant position remained vacant for two months. Forecast: 144,000, a saving of 6,000.
  • Office: 15,600 / 7 = 2,229 per month; forecast 26,743, an overspend of 2,743 due to the rent increase when the lease was renewed.
  • Equipment: balance of 600 dollars not needed.

Step 3: act before reallocating

Reallocation is not the first response. The team first decides on cost-control measures: grouping deliveries into monthly convoys instead of twice-monthly ones, and renegotiating the truck rental contract on a lump-sum basis. The logistician estimates the saving at 4,000 dollars over the remaining five months. The residual need for transport is therefore 15,486 - 4,000 = 11,486, rounded to 11,500 dollars.

Step 4: check contractual flexibility

Receiving headingInitial amount15% ceilingNeedProcedure
Transport38,0005,70011,500 (30.3%)Amendment required
Office24,0003,6002,700 (11.3%)Written notification sufficient

Step 5: the reallocation proposal

HeadingInitial budgetMovementRevised budgetJustification
Staff150,000- 6,000144,000Vacant position, no impact on activities
Distributions160,000- 7,600152,400Saving on unit price, targets maintained
Transport38,000+ 11,50049,500Fuel price increase and detour imposed by the road closure
Office24,000+ 2,70026,700Rent increase on lease renewal
Equipment20,000- 60019,400Unused balance
Total direct392,0000392,000Indirect costs unchanged

The amendment request is sent to the donor in month 8, accompanied by: a two-page note explaining the causes with evidence (fuel price monitoring from the Logistics Working Group, OCHA access report on the road closure), the table above, confirmation that the targets do not change, and the cost-saving measures already taken. The notification for the office heading can be included in the same request to avoid two separate exchanges.

The reasoning the donor expects: a quantified finding, a documented external cause, cost-control measures already taken, a solution that is neutral for the total budget and has no negative effect on results. A request that only says "transport is overspent, please accept the transfer" will be sent back or refused.

Step 6: allocating the shared rent

The rent for the Malanga office, 3,000 dollars per month, is shared among three projects according to the documented method, pro rata to the month's full-time equivalents. In March: project A (this project) 9 FTE, project B 6 FTE, project C 5 FTE, i.e. 20 FTE. Allocation: A 45% (1,350 dollars), B 30% (900 dollars), C 25% (750 dollars). The calculation is kept with the month's staff list, signed by human resources. If one donor has already funded the rent at 100% in its budget, the other two projects cannot charge any share of it: this is the double funding check.

Step 7: follow-up

Once approved, the revised budget is entered in the accounting system as the new baseline, with the initial version kept for traceability. The final report will show both columns, initial budget and revised budget, with the amendment reference.

8Common mistakes, auditor expectations and adapting to context

The most costly mistakes

MistakeConsequencePrevention
Request approval dated after the invoicePurchase deemed unauthorised; procedure not followedThe accountant refuses any verification without prior approval; register of numbered requests
Supporting documents kept as photocopies without the originalRisk of double charging; cost disallowedOriginal in the file of the paying project; certified copy for the others, with a note of the charging
Purchases split to stay below a thresholdNon-compliance with the procurement procedure, suspicion of favouritismAnnual procurement plan; monitoring of cumulative purchases by supplier and by month
Salaries charged at the budget percentage without timesheetsPartial or total disallowance of shared salariesMonthly timesheets, quarterly adjustment of charges
Expenditure committed in the final weeks to "use up the budget"Costs deemed unnecessary or outside the period (delivery after the end date)Spending plan from month 6; internal commitment deadline 45 days before the end
Financial report that does not agree with the accountsLoss of trust; extended auditReport generated from the accounting system, with a signed reconciliation table
Exchange rate applied case by caseUnjustified exchange gains or losses; unexplainable differencesWritten exchange rate policy, consistent with each contract
Staff advances not cleared at project endUnjustified expenditure to be refundedMonthly ageing analysis; final pay withheld until clearance

What auditors and donors look at

  • The audit trail: start from a line in the financial report, go down to the general ledger, then to the entry, then to the voucher, and back up. Every level must agree.
  • Samples: the auditor selects entries according to a method (high amounts, random selection, end-of-period entries, manual entries, adjustments). An NGO cannot predict the sample: everything must be ready.
  • End-of-project entries: expenditure in the final month, transfers between projects, reclassifications. These are the most scrutinised.
  • Consistency with the narrative: a narrative report announcing 2,400 households served alongside distribution spending at 60% raises questions.
  • Suspense accounts and reconciliation differences: their prolonged existence is an indicator of weak control.

Variations according to context

ContextWhat changesRecommended adaptations
Sudden-onset emergency (first weeks)Pressure to pay quickly, simplified procurement procedures, rapid recruitmentActivate in writing the emergency procedures provided for in the policy and the contract (limited duration, precise thresholds); document each waiver at the time it is granted; regularise files within 30 days
Protracted crisisMultiple projects, successive renewals, control fatigueQuarterly reviews of controls, task rotation, targeted internal audits, attention to costs that straddle two successive contracts
CampConcentrated payments, strong presence of intermediaries (leaders, committees)Direct payments to suppliers and daily workers, verified attendance lists, unannounced visits
Urban settingBanks and mobile money available, inflation and variable rentsKeep cash to a minimum; monthly monitoring of reference prices; leases with a regulated review clause
Remote managementNo international staff on site, physical controls difficultSupporting documents scanned weekly, third-party monitoring, cash counts by video call, enhanced consistency checks at the country office
High insecurityRisk of cash theft, extortion, seizureLow cash ceiling, split transfers, safe, discretion about paydays, procedure for reporting loss or theft with a police report where possible
Local partner with low capacityManual accounting, little-trained staff, dependence on one personShort tranches, verification of supporting documents before the next tranche, monthly accompaniment, simple templates (cash book, bank book, expense form), costed capacity-strengthening plan
Economy with multiple exchange rates or high inflationGap between official and parallel rates, rapid loss of valueStrictly apply the contract rules and national regulations; consult the donor before any transaction on an unofficial market; convert as needed; budgets denominated in hard currency where permitted

In an emergency, flexibility is allowed; the absence of a paper trail never is. A written waiver, signed and dated at the time of the decision, is worth more than an explanation drafted six months later for the auditor.

9Reusable toolkit: checklists and templates

Checklist for an expenditure voucher before payment

  1. The request is approved by the right person, according to the delegation of authority, and dated before the commitment.
  2. The budget sign-off shows the project code and budget line, and the balance is sufficient.
  3. The procurement procedure matches the threshold (number of quotations, bid analysis signed by a committee where required).
  4. The purchase order or contract is signed before delivery.
  5. The goods received note is signed by a person other than the buyer and states quantities and condition.
  6. The invoice is an original, in the organisation's name, with number, date, supplier details, breakdown of quantities and unit prices, and matches the order.
  7. The supplier has been screened against the applicable sanctions lists and is on the supplier database.
  8. The amounts are recalculated (quantity × price, totals, taxes).
  9. The payment method complies with the policy (bank transfer or cheque above the cash payment threshold).
  10. The voucher is stamped "paid", with date, project code and entry number.

Cash count report template

DenominationQuantityAmount
10,000……
5,000……
2,000……
1,000 and below……
Physical total (A)…
Signed IOUs (B), listed in an annex…
Theoretical cash book balance (C)…
Difference (A + B - C)…
Explanation of the difference…
Date, time; name and signature of the cashier; name and signature of the independent verifier…

Month-end closing checklist

CheckDoneByDate
Cash count reports from all bases received and signed
Bank reconciliations for all accounts, signed by the preparer and the reviewer
Reconciliation of the mobile money account with the operator's statement
Ageing analysis of staff advances, reminders sent
Suspense accounts cleared or justified
Payroll reconciled with the staff list
Shared cost allocation calculated and recorded
Exchange differences calculated according to the policy
Sample review of coding (at least ten entries per project)
Budget versus actuals reports produced and discussed with project managers
Closing file sent to headquarters

Variance commentary template for the budget versus actuals report

LineBurn rateCause of the varianceEnd-of-project forecastProposed actionOwner and deadline
3.1 Fuel82%28% price increase and 140 km detour53,500 (+ 40%)Grouping of convoys; amendment requestLogistician, project manager; end of month 8
…

The "end-of-project forecast" column is the most useful and the most often forgotten: a burn rate says nothing without a forecast. The forecast combines actuals, signed commitments and the remainder to be committed according to the activity plan.

Simplified delegation of authority matrix

Commitment amount (in US dollars)RequestApprovalPayment (bank signatories)
Up to 500Activity leadBase managerCash, one signature
500 to 5,000Project managerProgramme coordinator and finance sign-offTwo signatures
5,000 to 25,000Project managerCountry director and finance manager sign-offTwo signatures, one of them from senior management
Over 25,000Programme coordinatorCountry director after procurement committee review; headquarters according to the policyTwo signatures, one of them from senior management

These thresholds are indicative: each organisation sets them according to its size, its risks and its donors' requirements, and reviews them at least once a year.

10Interview questions and key references

Interview questions

1. "The month-end bank reconciliation shows an unexplained difference of 1,200 dollars. What do you do?"

A strong answer describes an orderly approach: check that both balances are at the same date, tick off the statement and ledger transactions one by one, look for the classic errors (transposed digits, duplicate entry, wrong bank account, transaction recorded in the wrong month), and examine old outstanding cheques. The candidate specifies that they do not post an adjusting entry without an explanation, that they inform the finance manager if the difference persists, and that they would consider reporting the matter if the anomaly suggests manipulation.

2. "A project manager asks you to charge expenditure to a project that still has budget, although it relates to another project that has ended. How do you respond?"

The candidate refuses clearly and explains why: non-compliant charging, risk of double funding or ineligible costs, risk to the donor relationship. They propose legitimate solutions: check whether the expenditure can be covered by unrestricted funds, examine whether part of it genuinely relates to the new project using a documented method, or plan ahead for the closure of the next project. They mention escalation to the finance manager if the pressure continues.

3. "In month 9, the project's burn rate is 45%. What questions do you ask?"

The candidate asks for the end-of-project forecast, the signed commitments and the schedule of remaining activities, and distinguishes delay (activities postponed but feasible) from savings (lower prices) and under-implementation (activities dropped). They propose a no-cost extension request if activities have been postponed, or a reallocation towards useful activities, informing the donor early.

4. "How do you allocate the costs of an office shared between four donors?"

The candidate presents an objective method (headcount, actual usage), written and approved, applied consistently every month, with calculations kept on file. They check that each donor accepts this type of cost in its budget, that the total does not exceed 100%, and that no donor is already funding the same cost in full.

5. "What are your three priorities when you arrive in a mission whose accounting is six months behind?"

A convincing answer: first secure the cash and bank accounts (cash count, reconciliations, signatories), then catch up on data entry in order of donor reporting deadlines, and finally re-establish the month-end closing with a realistic timetable. The candidate mentions informing headquarters, assessing the risk of ineligible costs and a possible need for temporary surge support.

Key references

  • Code of Federal Regulations, Title 2, Part 200 (Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards), in particular Subparts D and E, 2024 revision: United States Government.
  • Humanitarian Framework Partnership Agreement and its annexes (general conditions, eligibility rules, procurement procedures): Directorate-General for European Civil Protection and Humanitarian Aid Operations (DG ECHO), European Commission.
  • Financial Regulation applicable to the general budget of the Union: European Union.
  • Country-Based Pooled Funds (CBPF) Operational Handbook: OCHA.
  • Harmonized Approach to Cash Transfers (HACT) framework: UNDP, UNICEF, UNFPA and WFP.
  • FCDO guidance on grant management and partner financial management.
  • Practical Financial Management for NGOs and other Mango resources on NGO financial management (Mango has joined Humentum).
  • Core Humanitarian Standard on Quality and Accountability (CHS), Commitment 9 on the responsible use of resources: CHS Alliance, Groupe URD and the Sphere Project.
Scenario

The cash box that does not balance

Field office

Your role

You are a finance officer. The end-of-month cash count shows 640 dollars less than the cash book balance.

The cashier says he gave advances to colleagues “pending supporting documents”. The financial report to the donor is due in five days.

  1. Decision 1 of 3What do you do first?

  2. Decision 2 of 3How do you deal with the advances?

  3. Decision 3 of 3The report to the donor is due. What do you do?

Exercise: a budget versus actual report

Using this annual budget of 120,000 dollars divided into five lines (staff 50,000, activities 40,000, transport 12,000, office 8,000, indirect costs 10,000) and cumulative expenditure at month 6 of 30,000, 8,000, 11,000, 4,000 and 5,000, calculate the burn rates, identify the lines at risk and draft three recommendations.

Key points

  • No supporting document, no eligible expense.
  • Budget codes and cost codes on every entry.
  • Cash counts by two people and monthly bank reconciliation.
  • A budget versus actual report every month, compared with the time elapsed.

💼 Finance, HR and admin jobs

Put this course into practice: the latest jobs in this field.

See all 305 Finance, HR and admin jobs →

Prepare for the written test and interviewA model written test in this field, interview questions with sample answers and the STAR method.See the model test →
Further reading: course references
  1. Humentum (formerly Mango) (2021). Mango: financial management guides for NGOs. www.humentum.org
  2. IAASB (2022). International Standards on Auditing (ISA). www.iaasb.org
  3. CHS Alliance, Groupe URD, Sphere (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org
  4. United Nations Office for Project Services (2023). Zero-tolerance policy on fraud and corruption (example). www.unops.org

Daily quiz

3 questions to check what you have learned. Answer them all to complete the day.

1A bank reconciliation compares:
2Stamping “paid” on an invoice serves to:
3In month 6 of 12, a line is 10% spent. This is:

← OverviewDay 2 →