- Move from a problem tree to a theory of change.
- Build a logframe: objectives, results, activities, assumptions.
- Check the vertical and horizontal logic.
1From problem tree to objective tree
The problem tree places the core problem at the trunk, its causes in the roots and its consequences in the branches. Example: “high rate of diarrhoea among children under 5”, caused by unsafe water, lack of latrines and poor hygiene practices.
The objective tree turns each statement into a positive situation: “households have access to safe drinking water”, “households use latrines”. The branches on which the organisation can act are then selected: this is the strategy analysis.
2The theory of change
A theory of change explains how and why the activities will lead to the desired change. It reads as a chain of “if… then…” statements:
If we rehabilitate water points and train management committees, then households will have access to safe drinking water; if they also adopt handwashing, then diarrhoea among children will decrease, provided that spare parts remain available and the security situation allows access.
The “provided that” statements are the assumptions: they must be monitored, because if they fail, the project logic fails with them.
3The results chain
- Inputs: money, staff, materials.
- Activities: what the team does (train, distribute, build).
- Outputs: direct, controllable results of the activities (300 kits distributed, 40 community volunteers trained).
- Outcomes: changes in behaviour, access or practices among beneficiaries (75% of households treat water at home).
- Impact: the long-term change to which the project contributes together with other actors (reduced child mortality).
A common mistake: writing an activity instead of an outcome (“organise awareness sessions” is not an outcome).
4The logframe
The logical framework (logframe) summarises the project in a matrix of 4 rows and 4 columns.
| Intervention logic | Indicators | Means of verification | Assumptions | |
|---|---|---|---|---|
| Overall objective | Contribute to reducing water-related morbidity in the area | Prevalence of diarrhoea among children under 5 | Health district data | — |
| Specific objective | Targeted households have sustainable access to safe drinking water and good hygiene practices | % of households using an improved source | Baseline and endline surveys | Security allows access |
| Results | R1: 20 water points rehabilitated and managed by committees | Number of functional water points | Technical reports, visits | Spare parts available on the market |
| Activities | Rehabilitation, committee training, awareness-raising | Means and budget | Financial reports | No supply disruption |
Vertical logic: read from bottom to top, “if the activities are carried out and the assumptions hold, then the results are achieved…”. Horizontal logic: each level has its indicators, and each indicator has a realistic means of verification.
Detailed methods, a complete worked example, tools, common mistakes and interview questions.
5Facilitating a theory of change workshop: the complete method
A theory of change written alone at a desk by the proposal writer is almost always a list of activities joined by arrows. A real theory of change is the product of collective work that brings together the knowledge of the team, partners, technical services and, as far as possible, affected people. Here is a proven method for a one- to one-and-a-half-day workshop.
Preparation (one to two weeks before)
- Participants: 10 to 20 people. Project manager, sector technical leads, MEAL, finance (for realism), one or two partners, a representative of the government technical services if the context allows. Communities are consulted beforehand through focus group discussions whose findings are presented at the workshop.
- Inputs: needs assessment, cluster data, the country's Humanitarian Needs Overview (HNO) and Humanitarian Response Plan (HRP), evaluations of previous projects, literature reviews on what works in the sector.
- Core problem: formulated in advance in a precise and verifiable way, with the population concerned (for example "31% of children aged 6 to 59 months in the municipalities of Bari and Tolo suffer from global acute malnutrition").
Workshop agenda
- Define the long-term change (45 minutes): what will the situation look like if the problem is solved? The desired change is written in one sentence, then the share the project can reasonably influence is delineated.
- Backwards mapping (2 hours): starting from the long-term change, ask "what needs to happen just before for this to occur?". Each answer is a precondition, written on a card as a state ("mothers practise exclusive breastfeeding"), never as an activity. The question is repeated for each precondition until the output level is reached.
- Check necessity and sufficiency (1 hour): for each link, two questions. Is this precondition necessary? Is the set of preconditions sufficient, or is something missing that other actors need to do?
- Define the scope (45 minutes): draw a line of accountability. Below it, what the project commits to deliver; above it, what it contributes to. Preconditions beyond the project's reach are assigned to other actors or become assumptions.
- Make assumptions and evidence explicit (1 hour 30): for each arrow, why do we think A leads to B? What evidence do we have (previous evaluation, study, team experience)? Assumptions without evidence become learning questions.
- Identify the activities (1 hour): only at this stage are the interventions needed to produce the basic preconditions listed.
- Write the narrative (after the workshop): one to two pages telling the logic in "if… then… because… provided that…" form, accompanied by the diagram.
The "because" test: for each arrow in your diagram, a participant must be able to complete the sentence "A leads to B because…" by citing evidence or experience. An arrow without a "because" is an assumption to be tested, not a certainty.
Causal assumptions and external assumptions
Two families of assumptions must be distinguished. Causal assumptions concern the internal logic ("if mothers know the feeding practices, they will apply them"): they are often wrong, because knowledge is not enough when time, money or decision-making power is lacking. External assumptions concern the environment ("food prices remain stable", "access remains possible"). The "assumptions" column of the logframe usually contains only the latter; the theory of change, on the other hand, must make the former visible, because they explain most failures.
6Full example: from analysis to the logframe of a nutrition and WASH project
Fictional context: the NGO "Action Santé Sahel" is preparing a 12-month project in the municipalities of Bari and Tolo (fictional district of Kanem-Est). The nutrition survey using the SMART methodology measured global acute malnutrition (GAM) of 16.2% among children aged 6 to 59 months, above the 15% emergency threshold used by WHO and the Nutrition Cluster. The causal analysis (of the "Link NCA" type) identified three groups of causes: inadequate infant feeding practices (exclusive breastfeeding at 22%), a high incidence of water-related diarrhoea (only 38% of households use an improved water source) and low treatment coverage (estimated at 41%, whereas the Sphere standard aims for over 50% in rural areas).
Step 1: from the problem tree to strategic choices
The team selects three areas in which it has added value and funding: coverage of acute malnutrition treatment, access to safe drinking water and feeding practices. The food security component is left to another cluster partner that distributes cash transfers in the same municipalities: this complementarity becomes an assumption.
Step 2: the theory of change narrative
If cases of acute malnutrition are detected early by community health volunteers and treated in well-supplied health centres, if households have access to sufficient quantities of safe drinking water and treat it correctly, and if mothers and caregivers adopt exclusive breastfeeding and appropriate complementary feeding, then morbidity and acute malnutrition among children under 5 will decrease, because diarrhoea and inadequate feeding are the two main immediate causes identified by the causal analysis, provided that nutrition supplies are delivered without stock-outs by the national supply chain and that the partner's cash transfers reduce household food insecurity.
Step 3: the complete logframe
| Level | Intervention logic | Indicators (baseline → target) | Means of verification | Assumptions |
|---|---|---|---|---|
| Overall objective | Contribute to reducing malnutrition-related mortality and morbidity among children under 5 in Kanem-Est district | GAM prevalence among children aged 6-59 months (16.2% → downward trend) | Annual cluster SMART surveys | — |
| Specific objective | Children aged 6 to 59 months in Bari and Tolo benefit from quality prevention and treatment of acute malnutrition | SAM treatment coverage (41% → 60%); cure rate among children discharged from the programme (baseline 71% → over 75%, Sphere standard), death rate (under 10%), defaulter rate (under 15%) | Coverage survey (SQUEAC method), registers and monthly reports from the centres | Supplies (ready-to-use therapeutic food) are delivered without stock-outs; secure access is maintained |
| Result 1 | Cases of acute malnutrition are detected and referred early | Number of children screened by mid-upper arm circumference measurement (target 18,000 screenings); % of admissions with a MUAC above 105 mm, a sign of early detection (baseline 35% → 55%) | Screening forms, admission registers | Volunteers remain motivated despite not being paid |
| Result 2 | Households have access to sufficient quantities of safe drinking water | Number of functional water points (12); % of households with at least 15 litres per person per day (baseline 46% → 75%); % of water samples at point of consumption free of faecal coliforms (baseline 30% → 70%) | Water point monitoring forms, household survey, water testing | Spare parts remain available on the local market |
| Result 3 | Caregivers apply recommended infant feeding practices | % of children under 6 months exclusively breastfed (22% → 40%); % of children aged 6 to 23 months receiving minimum dietary diversity (baseline 18% → 30%) | Household survey (standard infant and young child feeding module) | Households can afford diversified food (partner's cash transfers maintained) |
| R1 activities | 1.1 Train 120 volunteers in screening; 1.2 monthly door-to-door screening; 1.3 referral and counter-referral system | Means: staff, MUAC tapes, training, budget EUR 210,000 | Financial and activity reports | Health authorities validate the protocol |
| R2 activities | 2.1 Rehabilitate 12 water points; 2.2 train 12 management committees; 2.3 distribute household water treatment products | Means: WASH team, materials, budget EUR 340,000 | Financial and activity reports | Communities make land available |
| R3 activities | 3.1 Mother-to-mother support groups; 3.2 cooking demonstrations; 3.3 targeted home visits | Means: female facilitators, materials, budget EUR 95,000 | Financial and activity reports | Mothers-in-law and husbands agree to take part |
Step 4: consistency checks
- Vertical logic: is Result 3 enough to change feeding practices? The workshop showed that mothers-in-law often decide how infants are fed. Activity 3.1 was therefore extended to grandmothers, and a causal assumption ("mothers' knowledge is enough") was turned into a learning question.
- Horizontal logic: the coverage indicator requires a SQUEAC survey, which costs about EUR 15,000. It was added to the budget; without it, the indicator could not be measured.
- Realistic targets: going from 22% to 40% exclusive breastfeeding in 12 months is ambitious but documented by comparable projects in the region; a 60% target would have been judged unrealistic by a proposal reviewer.
- Attribution and contribution: GAM is placed at the overall objective level, without a numerical target, because it also depends on food security, epidemics and the season. The project commits to treatment coverage and quality.
7The results frameworks of the main donors
All donors use results-based logic, but with different terminology, levels and requirements. A MEAL professional must be able to translate the same project into several formats without betraying its logic.
Terminology equivalences
| Generic level | Common English terminology | ECHO | FCDO | BHA |
|---|---|---|---|---|
| Overall objective | Goal, impact | Principal objective | Impact | Award goal |
| Specific objective | Outcome, purpose | Specific objective | Outcome | Sector objectives |
| Results | Outputs | Results | Outputs | Sub-sectors and interventions |
| Activities | Activities | Activities | Activities (often outside the logframe) | Activities |
Points of attention by donor
- ECHO: the Single Form structures the action into a principal objective, a specific objective and results, with indicators at each level. ECHO provides key results indicators (KRIs) and key outcome indicators by sector, which should be preferred when they fit the action, because they allow aggregation at global level. Custom indicators are possible but must be precisely defined. The gender-age marker and the resilience marker are self-assessed in the proposal and then checked at the final report: promising disaggregation that cannot be delivered lowers the marker score.
- BHA (the US Government's Bureau for Humanitarian Assistance): the proposal is organised by sectors and sub-sectors; each sub-sector selected triggers mandatory indicators described in the BHA indicator handbook, supplemented by custom indicators. A MEL plan is required, whose level of detail increases with duration and award value; longer awards generally require baseline and endline surveys for outcome indicators. The rules change regularly: refer to the current version of the application guidelines.
- FCDO (United Kingdom): the logframe includes interim milestones and final targets, sources, assumptions and often output weightings. Annual reviews score each output and the programme on a scale from A++ (outputs substantially exceeded expectation) to C (outputs substantially did not meet expectation); repeated low scores can lead to restructuring or closure. The logframe is a living document, revised with FCDO's agreement.
- United Nations agencies (partnership funding, country-based pooled funds): indicators are generally aligned with the humanitarian response plan and the cluster monitoring frameworks. The Central Emergency Response Fund (CERF) and the country-based pooled funds managed by OCHA require standardised indicators, with figures for people targeted and reached disaggregated by sex, age and disability.
- European Union outside ECHO (development and transition programmes): the logframe matrix follows Commission guidance, with an intervention logic of impact, outcomes and outputs, and increasing use of indicators from the EU Results Framework.
Translation rule: first build the project's own theory of change, then map it onto the donor's format. Doing the reverse produces projects cut up according to the boxes of a form rather than the logic of change.
Logframes, results frameworks and alternative approaches
The logframe has well-known limitations: it assumes linear causality, relative stability of the context and predictable results. In highly volatile contexts or for advocacy, social cohesion or institutional strengthening programmes, other approaches complement the logframe without replacing it:
- Outcome mapping (outcome mapping): tracks changes in the behaviour of the "boundary partners" the project works with directly, graded as what one would expect to see, like to see and love to see.
- Outcome harvesting (outcome harvesting): collects observed changes after the fact, then works backwards to the project's contribution and verifies it with independent sources.
- Contribution analysis: builds, step by step, a plausible contribution story showing that the project contributed to the observed change, examining alternative explanations.
- Adaptive management: the logframe sets the objectives, but outputs and activities are revised at regular intervals based on monitoring data, with the donor's agreement. FCDO and BHA encourage this approach when the rationale is documented.
8Quality control of a logframe: the reviewer's checklist
When a donor reviews a proposal, or when an evaluator analyses a project's design, they apply a more or less formal checklist. Here it is, as a MEAL professional should apply it to their own logframe before submission.
20-point checklist
| No. | Checkpoint | Yes / No |
|---|---|---|
| 1 | The core problem is quantified and located, with the data source | |
| 2 | The overall objective is a change to which the project contributes, without claiming to achieve it alone | |
| 3 | There is only one specific objective (or a very small number, clearly distinct) | |
| 4 | The specific objective describes a change for people, not a service delivered | |
| 5 | Each result is an output under the project's control | |
| 6 | No result repeats the specific objective in other words | |
| 7 | The results, once achieved and if the assumptions hold, are sufficient to achieve the specific objective | |
| 8 | The activities are necessary and sufficient for each result | |
| 9 | Each level has 1 to 3 indicators, no more | |
| 10 | Outcome indicators measure a change in access, practice or situation | |
| 11 | Each indicator has a baseline value or a date and a method for obtaining it | |
| 12 | Targets are justified (standards, comparable projects, resources) | |
| 13 | Standard donor or cluster indicators are used where they exist | |
| 14 | Disaggregation by sex, age and disability is planned where it makes sense | |
| 15 | Each means of verification exists or is budgeted | |
| 16 | Assumptions are external and plausible, not conditions that are already certain or unlikely | |
| 17 | No "killer" assumption (if it is unlikely, the project must be redesigned, not written up as an assumption) | |
| 18 | The logframe is consistent with the budget and the workplan | |
| 19 | Protection and "do no harm" risks are taken into account | |
| 20 | The logframe is consistent with the humanitarian response plan and the cluster strategy |
The most common mistakes and how to correct them
| Mistake | Example | Correction |
|---|---|---|
| Activity at outcome level | "Raise hygiene awareness among 5,000 people" as the specific objective | "Targeted households adopt handwashing at critical times" |
| Logical leap | Seed distribution → reduced malnutrition | Add the missing links: harvested production, consumption, dietary diversity |
| Indicator without a denominator | "Increase in the number of households treating water" | "% of targeted households whose drinking water contains free residual chlorine" |
| Target without a baseline | "80% of households satisfied" | Measure the baseline at start-up or state the method and date |
| Assumption under the project's control | "Staff are recruited on time" | This is a management risk, to be addressed in the risk management plan |
| Killer assumption | "The conflict ends" in an area of active fighting | Rethink the design, plan scenarios and a flexible approach |
| Frozen logframe | No revision despite mass displacement of the target population | Request an amendment to the agreement, document the rationale |
Monitoring assumptions during implementation
An assumption written into the logframe and never reviewed is useless. For each assumption, define an indicator or a warning sign, a source and a review frequency. For example, for the assumption "nutrition supplies are delivered without stock-outs": indicator "number of weeks of stock available in health centres", reviewed every month, alert threshold below four weeks, planned response (alert to the Nutrition Cluster and UNICEF, reallocation between centres). Assumptions are reviewed at quarterly reviews, together with the indicator tracking table.
9Adapting the theory of change and the logframe to the context
| Context | Specific features | Adaptations |
|---|---|---|
| Sudden-onset emergency | The proposal is written in a few days; information is partial | Short logframe focused on outputs and coverage; simple one-paragraph theory of change; revision planned after the in-depth needs assessment, around weeks 6 to 8 |
| Protracted crisis | Successive projects with the same populations; expectations of sustainability and links with development | Multi-year theory of change; resilience and capacity indicators; alignment with development plans and humanitarian-development-peace nexus approaches |
| Camp | Concentrated services; aid dependency; governance through site management | Include site governance structures in the theory of change; service quality indicators based on Sphere standards |
| Urban setting | Functioning markets; existing public services; mobile population | A theory of change that builds on existing systems (markets, municipal services) rather than creating parallel services |
| Remote management | Limited capacity to verify outcomes | Fewer outcome indicators, but better measured; realistic means of verification; explicit learning questions |
| High insecurity | Intermittent access; mobile populations | Scenarios (normal, reduced, no access) and alternative activities planned from the design stage; security assumptions monitored monthly |
| Local partner in the lead | In-depth knowledge of the context; variable formal capacity | Co-design of the theory of change; logframe in the partner's working language; institutional strengthening indicators negotiated, not imposed |
Localisation in design
The Grand Bargain commitments (2016) provide for transferring more resources and decision-making power to local and national actors, with a target of 25% of humanitarian funding transferred as directly as possible. In practical terms, for MEAL, this means: involving the partner in designing the theory of change rather than only in implementation, recognising its own indicators and tools when they are of good quality, budgeting its MEAL costs and indirect costs, and including results on its institutional capacity in the logframe if it so wishes.
10Interview questions and key references
Interview questions
1. "What is the difference between a theory of change and a logframe?"
A good answer explains that the theory of change describes how and why change happens, including conditions outside the project's control and causal assumptions, whereas the logframe is a management tool summarising the project's commitments, indicators and sources. It specifies that one comes before the other and that the logframe contains only part of the theory of change.
2. "Here is a logframe. What weaknesses do you see?" (a common written test exercise)
The candidate methodically applies a checklist: confusion between levels, indicators without a denominator or baseline, assumptions under the project's control, logical leaps, unbudgeted means of verification. They propose precise rewordings, not general remarks.
3. "The context changes radically in the sixth month. What do you do with the logframe?"
It proposes a rapid review of the theory of change, documents the change in context with data, consults the donor early, prepares an amendment request (targets, activities, areas) and maintains traceability between the old and the new framework. It mentions the amendment clauses of agreements and adaptive management.
4. "How do you involve communities in designing a project in an emergency?"
It cites rapid and proportionate methods (focus group discussions separated by sex and age, consultation of existing committees, analysis of feedback from the first distributions), and shows how this information concretely changes the design. It acknowledges the limitations in emergencies and plans for later adjustment.
5. "Why not set a malnutrition reduction target in the specific objective of a 12-month project?"
It explains attribution and contribution, external factors (season, epidemics, food security), the difficulty of measuring significant change in 12 months, and proposes outcome indicators more directly under the project's influence (coverage, quality of treatment, practices).
Key references
- Better Criteria for Better Evaluation and documents on results-based management: OECD Development Assistance Committee.
- European Union guides on project cycle management and the logical framework.
- Single Form and guidance on key results indicators: ECHO.
- Emergency application guidelines and indicator handbook: BHA.
- FCDO guidance on logframes and annual reviews.
- The Sphere Handbook (2018): standards and key indicators by sector.
- Outcome Mapping (IDRC, Canada) and Outcome Harvesting (Ricardo Wilson-Grau).
- Grand Bargain commitments (2016) and follow-up documents on localisation.
The logframe for a nutrition project
Rural district, Horn of Africa
You are helping to draft the logframe for a project treating acute malnutrition among children under 5.
The team has written as the specific objective: “Distribute 12,000 sachets of therapeutic food”. The donor asks for the intervention logic to be revised.
Decision 1 of 3What is wrong with this specific objective?
Decision 2 of 3Which assumption is the most important to include between “children screened and admitted” and “children cured”?
Decision 3 of 3The country director wants to add the impact “Eradicate poverty in the region”. What do you suggest?
Key takeaways
A sound logframe distinguishes activities, outputs, outcomes and impact, and makes visible the assumptions on which success depends.
Exercise: your logframe
Choose a problem in your area (malnutrition, school dropout, gender-based violence…). Draw the problem tree with three causes, turn it into an objective tree, then fill in the “intervention logic” column of a logframe: one specific objective, two results and three activities per result. Add two assumptions.
Key points
- A theory of change explains the how and the why.
- Output = what we deliver; outcome = what changes for people.
- Assumptions are monitored just like indicators.
- The logframe is read from bottom to top.
💼 Monitoring, evaluation and data jobs
Put this course into practice: the latest jobs in this field.
- Project Completion, Monitoring and Partnerships Consultant (Korean Language Preferred)International Trade Centre · Uganda
- MERL Officer- RosterPlan International · Ethiopia
- Expert(e) en Suivi-Évaluation et Pilotage de la Performance des Entreprises AccompagnéesONUDI / UNIDO · Comoros
- National Monitoring and Evaluation ExpertONUDI / UNIDO · Palestine
- Head of Section (Mathematics) / Senior Research ScientistUNESCO · Italy
Further reading: course references
- OECD-DAC (2019). Better Criteria for Better Evaluation: Revised Evaluation Criteria Definitions and Principles for Use. www.oecd.org/fr/cad/evaluation/criteres-cad-evaluation.htm
- ALNAP (Buchanan-Smith, Cosgrave, Warner) (2016). Evaluation of Humanitarian Action Guide. www.alnap.org/help-library/evaluation-of-humanitarian-action-guide
- CHS Alliance, Groupe URD, Sphere (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org
- Sphere Association (2018). The Sphere Handbook: Humanitarian Charter and Minimum Standards in Humanitarian Response. spherestandards.org/fr/manuel-2018
- United Nations Evaluation Group (UNEG) (2016). Norms and Standards for Evaluation. www.unevaluation.org
Daily quiz
3 questions to check what you have learned. Answer them all to complete the day.