Day 1 of 3 · 6 hours · Level 1 Beginner

Scoping the project

Learning objectives for today
  • Know the phases of the project cycle.
  • Analyse stakeholders.
  • Manage the triple constraint: scope, schedule, cost (and quality).

1Project, programme and the role of the project manager

A project is a temporary endeavour, with a beginning and an end, that produces a unique result (for example rehabilitating 20 water points in 12 months). A programme groups several related projects that serve the same broader objective.

The project manager does not do everything personally: they organise the work, coordinate the teams and support services (logistics, finance, HR), monitor progress and report to management, the donor and communities.

2The phases of the project cycle

Sector guides (such as PMD Pro) describe successive phases, with monitoring, evaluation and control running throughout the project:

  1. Identification and definition: analysis of needs, context and options; intervention logic (logframe).
  2. Set-up: project charter, team, governance, kick-off meeting.
  3. Planning: detailed work plan, budget, procurement, risks, monitoring and evaluation, communication.
  4. Implementation: carrying out activities, managing the team and partners.
  5. Closure: final delivery, reports, handover, lessons learned, administrative close-out.

A decision taken at the start costs little to change; the same decision changed at the end of the project is very expensive. Hence the importance of scoping.

3Stakeholders

A stakeholder is any person or organisation that influences the project or is affected by it: communities, local authorities, donor, partners, clusters, team, suppliers.

The influence / interest matrix helps decide how to work with each one:

Low interestHigh interest
High influenceKeep satisfied (inform regularly)Manage closely (involve in decisions)
Low influenceMonitorKeep informed and consult

Affected communities often have little formal power but maximum interest: accountability requires consulting them and reporting back to them.

4The triple constraint

Every project balances three linked parameters: scope (what is delivered), schedule and cost, with quality at the centre. If one changes, at least one other must move: delivering more latrines with the same budget requires more time, or reduces quality.

The project charter (one to two pages) sets these parameters, the objective, the deliverables, the main risks, the budget and who decides what. It is approved by management before planning begins.

In-depth course

Detailed methods, a complete worked example, tools, common mistakes and interview questions.

5From needs assessment to intervention logic

Scoping does not start with the charter: it starts with the question "what problem, for whom, and why us?". A poorly identified project will never be rescued by good planning. The identification and design phase turns needs data into an intervention logic that can be defended before a donor, a cluster and the communities.

Step 1: start from existing data before producing new data

Before launching an assessment, the project manager gathers what already exists: the country's Humanitarian Needs Overview (HNO) and Humanitarian Response Plan (HRP), cluster sector analyses, the findings of the Multi-Cluster/Sector Initial Rapid Assessment (MIRA) if the crisis is recent, displacement tracking data (IOM DTM), food security reports (IPC analysis), and other organisations' assessments available through the cluster. The Joint Intersectoral Analysis Framework (JIAF) provides needs severity by area and population group: a project that targets a severity 2 area while the neighbouring area is classified 4 will have to explain why.

Field rule: every additional assessment takes up the time of affected people. "Assessment fatigue" is a real accountability problem. Collect only what is missing, and coordinate it with the cluster.

Step 2: the targeted complementary assessment

  • Secondary data: a 3 to 5-day desk review, summarised in a 2 to 4-page note (context, population, needs by sector, existing capacities, information gaps).
  • Primary data: key informant interviews (authorities, leaders, women leaders, health workers, teachers), focus group discussions separated by sex and age, direct observation, technical measurements (water point yield, water quality, condition of infrastructure), household survey if needed.
  • Minimum disaggregation: sex, age (brackets compatible with the cluster), disability (Washington Group Questions), status (IDP, returnee, host community).
  • Protection and gender analysis: access risks, risks linked to the location of facilities (lighting, distance, privacy), power dynamics. It shapes the design, not just the report.
  • Market analysis if the cash option is feasible: availability of goods, prices, traders' capacity to absorb demand, physical access to markets.

Step 3: analyse the problem

The problem tree puts the core problem at the trunk (for example "high incidence of diarrhoeal disease among IDPs in Kalema"), the causes at the roots (insufficient quantity of water, water contaminated at the point of consumption, open defecation, no handwashing at critical times) and the effects in the branches (morbidity, malnutrition, health expenditure). It is built in a workshop with the team, partners and community representatives. Turned around, it becomes an objective tree: each cause becomes a result to achieve.

You never tackle every root. The analysis of options keeps those that match the organisation's mandate, its added value, the gaps identified by the cluster, the likely budget and feasibility (access, season, timeframes). The roots set aside must be covered by other actors or listed as assumptions.

Step 4: formalise the intervention logic

The theory of change explains the "how and why": if we do X, then Y will happen, because of Z (causal assumption). The logical framework condenses it into a matrix required by most donors:

LevelIntervention logicIndicatorsMeans of verificationAssumptions
Overall objective (impact)Contribute to reducing water- and sanitation-related morbidityIncidence of diarrhoea among children under 5 (health district data)Health information system—
Specific objective (outcome)Targeted households have safe, dignified and sustainable access to water, sanitation and hygiene% of households using at least 15 L/person/day; % of households with E. coli-free water at the point of consumptionHousehold surveys, water testsNo new mass influx exceeding planned capacity
Results (outputs)Water points rehabilitated and managed; latrines built; hygiene practices strengthenedNumber of functional water points; people-to-latrine ratio; % of households with a handwashing facilityHandover certificates, technical monitoringMaterials available on the regional market
ActivitiesStudies, procurement, works, committee training, awareness-raisingMeans and costs (see budget)Physical access maintained in the dry season

The vertical logic is tested from the bottom up: if the activities are carried out and the assumptions hold, are the results achieved? If the results are achieved and the assumptions hold, is the specific objective achieved? An assumption judged both very likely to be false and decisive is a "killer assumption": the design has to be revised, not the assumption written in the box.

Step 5: align with standards

The intervention logic must show that it aims for recognised standards. For a WASH project, the Sphere minimum standards give precise benchmarks: at least 15 litres per person per day for drinking, cooking and hygiene; a maximum of 250 people per tap (flow of 7.5 L/min), 500 per hand pump (17 L/min) and 400 per open well; a water point less than 500 metres from the dwelling; queuing time of less than 30 minutes; one latrine per 50 people in the initial phase, then one per 20 as soon as possible; latrines less than 50 metres from shelters and at least 30 metres from groundwater sources; free residual chlorine of 0.2 to 0.5 mg/L at the point of delivery, with higher values recommended during diarrhoeal disease outbreaks. The Core Humanitarian Standard (CHS) adds quality and accountability commitments: a response that is appropriate, effective, strengthens local capacities, is based on communication and participation, and has complaints mechanisms.

The national cluster often adapts these benchmarks (cluster indicators, minimum packages, reference costs). The project manager should use the cluster's indicators as much as possible: this makes reporting easier (4W/5W tool) and allows comparison between partners.

6The project charter in detail and governance

The charter is the project's internal contract. It formally authorises the start, gives the project manager authority and sets the scope against which they will be judged. In many NGOs it takes the form of a project launch sheet approved by the country director, drawn up from the proposal accepted by the donor and the signed agreement.

Contents of a complete charter

HeadingExpected contentMain source
IdentificationTitle, project code, donor, agreement reference, contractual start and end dates, area, sectorSigned agreement
RationaleProblem, target population quantified and disaggregated, link with the response plan and the country strategyProposal, HRP
Objectives and resultsSpecific objective, results, indicators with baseline values and targetsLogical framework
ScopeDeliverables included and, above all, explicit exclusions (what the project will not do)Proposal, analysis of options
Milestones5 to 10 major milestones with dates (end of baseline survey, contract awards, completion of works, interim report…)Work plan
BudgetTotal amount, breakdown by main heading, co-funding, indirect cost rate, key eligibility rulesContractual budget
Constraints and assumptionsSeason, access, import procedures, donor rules, partner capacitiesContext analysis
Major risksThe 5 to 8 main risks and their ownersInitial risk register
GovernanceWho decides what, delegation thresholds, steering committee, review frequencyInternal policies
Contractual obligationsReporting schedule, visibility, audit, procurement rules, asset management, record retentionDonor general conditions
SignaturesProject manager, programme coordinator, country director, finance manager—

Read the agreement before writing the charter

The classic mistake of a newly arrived project manager is to work from the proposal without reading the agreement and its annexes. Yet it is the general conditions that determine what will be checked during an audit. The main institutional donors share common features:

  • Eligibility period: only expenditure incurred between the start and end dates is eligible, unless there is an express retroactivity clause.
  • Budget flexibility: transfers between budget headings are allowed without prior approval up to a certain threshold set in the agreement; beyond that, a formal amendment is required. For US funding subject to 2 CFR 200, section 200.308 governs the revisions that require prior approval (change in scope or objectives, change in key personnel, significant transfers between cost categories).
  • Procurement rules: competition thresholds, origin rules, exclusion lists and sanctions screening.
  • Indirect costs: for European Union humanitarian aid, a capped percentage of eligible direct costs is set by the partnership (around 7%); for US funding, a negotiated rate (NICRA) or a de minimis rate provided for in the regulations; United Nations agencies apply their own rates in partnership agreements.
  • Reports: interim, final, financial; deadlines (for example 120 calendar days after the end for the final report under 2 CFR 200.344, three months for many European donors).
  • Visibility: logo and communication obligations, with a possible waiver for security reasons, to be requested in writing.

Governance: who decides what

Clear governance prevents every decision from going up to the country director or, conversely, decisions that commit the organisation from being taken alone in the field. It is formalised in three elements.

  1. The steering committee: programme coordinator (chair), project manager, finance manager, logistics manager, MEAL focal point, local partner representative. A monthly 60 to 90-minute meeting, based on a one-page dashboard. It rules on significant variances, approves internal change requests and decides on escalation to the donor.
  2. The delegation of authority matrix: signature and commitment thresholds (for example purchase orders up to EUR 5,000 signed by the project manager, up to EUR 25,000 by the coordinator, above that by the country director), recruitment authority, authority to modify the work plan.
  3. The review schedule: weekly team meeting, monthly budget review with finance (budget versus actuals and forecast), quarterly risk review, formal mid-term review.

The kick-off meeting

It is held within the first two weeks after signature. Half a day is enough if it is well prepared. Typical agenda: recap of the context and intervention logic; walk-through of the contractual obligations (procurement, visibility, reporting, eligibility) by the finance manager; presentation of the milestones and the provisional critical path; allocation of roles; major risks; upcoming deadlines. The minutes, with decisions and action points, are circulated within 48 hours. A separate, shorter kick-off session is held with the partner and another with the local authorities.

A project that starts without the support services having read the agreement starts with ineligible expenditure in the making. The internal kick-off is as much a compliance exercise as a mobilisation exercise.

7In-depth stakeholder analysis and accountability

The influence/interest matrix from the core course is a starting point. To really manage a project, you need to move from a snapshot to an engagement plan: for each actor, what we expect from them, what they expect from us, how and how often we communicate, and who in the team is responsible.

A five-step method

  1. List broadly in a workshop (90 minutes), by category: affected populations (IDPs, hosts, groups facing specific risks), authorities (administrative, technical, customary), armed actors or actors controlling territory where relevant, coordination (cluster, OCHA, cash working group), other organisations present, private sector (suppliers, transporters, mobile network operators), donor, headquarters, team and partner.
  2. Characterise each actor: interest, influence, expected position (supportive, neutral, opposed), expectations, concerns, capacity to block the project.
  3. Position them in the matrix and identify the actors who may change quadrant during the project (a newly appointed local authority, an armed group taking control of a road).
  4. Define the engagement: inform, consult, involve, collaborate, delegate. The level depends on the actor and on the decision concerned.
  5. Update quarterly and after any major change in context.

Stakeholder engagement plan: template

ActorPositionExpectations / concernsLevel of engagementChannel and frequencyResponsible
IDP site committeesSupportiveSpeed, fair targeting, daily labour opportunitiesCollaborateFortnightly meeting, notice boards, feedback on complaintsAccountability officer
Host communityNeutral to reluctantAccess to the new water points, pressure on resourcesConsult, then involveMonthly meeting with the village chief, joint water point committeeProject manager
Water department technical serviceConditionally supportiveCompliance with national standards, handover of facilitiesInvolveApproval of studies, joint handover inspectionWASH engineer
WASH ClusterSupportive5W reporting, no duplication, consistent costsInform and coordinateMonthly meeting, monthly 5W reportProject manager
DonorSupportiveCompliance, results, visibility, risk managementInform and consultContractual reports, quarterly check-in, monitoring visitProgramme coordinator
Local partnerSupportiveRecognition, running costs covered, capacity strengtheningCollaborateSteering committee, weekly operational meetingProject manager

Affected populations: from consultation to accountability

The CHS makes participation and accountability verifiable requirements. In practice, for the scoping phase:

  • Needs and priorities are gathered directly from women, men, girls and boys of different ages, persons with disabilities and marginalised groups, in spaces where they can speak freely.
  • Communities are informed about the organisation, its mandate, the project, its selection criteria and its limits, in languages and formats they understand.
  • A complaints and feedback mechanism is designed before activities start, consulting users on their preferred channels (box, toll-free hotline, help desk, committees), with a separate and confidential procedure for sensitive complaints, in particular sexual exploitation and abuse, in line with the IASC commitments on protection from sexual exploitation and abuse.
  • Response times are set and budgeted: for example acknowledgement of receipt within 7 days, a substantive response within 30 days for non-sensitive complaints, immediate referral (within 24 hours) of sensitive allegations to the designated focal point.

Accountability has a cost: dedicated staff, a hotline, translation, travel, team time. If it does not appear in the budget and in the WBS, it will not be implemented.

Sensitive actors and neutrality

In conflict settings, stakeholder analysis overlaps with security and access analysis. Any contact with de facto authorities or armed groups follows the organisation's humanitarian access and negotiation policy, is authorised by line management and documented. The analysis must also identify the risks of aid diversion and the project's effects on local tensions: this is the Do No Harm approach, which distinguishes dividers and connectors between groups and checks that the project does not reinforce the former.

8Full case study: scoping the Kalema WASH project

This fictional case is the common thread running through all three days. It follows, step by step, the reasoning of a project manager, from receipt of the agreement to approval of the charter.

The context

Kalema district, in the fictional province of Haut-Lomani. After clashes in the north of the province, some 18,000 internally displaced people (3,600 households of 5 people on average) have settled in three spontaneous sites around the town of Kalema, next to a host community of 12,000 people. Site A (8,000 people) is the oldest, site B (6,000) is peri-urban, site C (4,000) is 14 km away on a track cut off two months a year during the rains (July-August). The health centre reports a 60% increase in consultations for diarrhoea over three months. The fictional international NGO Alvéa works with a local partner, the Association Mbeka pour le développement (AMD), which is well rooted in the community but has little experience of institutional funding.

Baseline data

IndicatorSite ASite BSite CSphere standard
Water available (L/person/day)911615 minimum
Functional water points6 hand pumps4 pumps + 1 water kiosk1 open well500 people/pump; 400 people/open well
People per functional latrine9570more than 20050 (initial phase), then 20
Households with a handwashing facility12%18%5%Access to soap and water for all
Samples positive for E. coli at the point of consumption48%35%70%0 E. coli / 100 mL

The scoping reasoning

1. Size the needs. For the displaced population alone, reaching 500 people per pump requires 36 equivalent water points; 11 functional ones exist plus one kiosk. At a ratio of 50 people per latrine, 360 latrines are needed, then 900 in the longer term (1:20 ratio); around 210 are functional. The gap is therefore about 24 water points and 150 latrines in the initial phase, 690 in the longer term.

2. Check coverage by other actors. The cluster's 5W shows that another NGO has committed to 4 boreholes in site B and 100 latrines in site A. The residual gap brings Alvéa's target down to 20 water points (12 rehabilitations and 8 new boreholes fitted with pumps) and 600 shared family latrines (one for roughly four households, i.e. 20 people), across the three sites.

3. Make the scope trade-offs. The envelope announced by the donor is EUR 1,200,000 over 12 months. An initial estimate puts the cost of all identified needs at EUR 1,420,000. The project manager presents three options to the coordinator.

OptionScopeEstimated costAdvantagesDisadvantages
AFull package across the 3 sites, 12 monthsEUR 1,420,000Full coverageOver the envelope; uncertain search for co-funding
B3 sites, latrines reduced to 450, no shower constructionEUR 1,190,000Within the envelope, sites coveredLatrine ratio of 1:27 instead of 1:20; less dignity and protection
C3 sites, 600 latrines, hygiene kits replaced by cash transfers for hygiene after market analysisEUR 1,205,000Scope maintained, lower logistics costsMarket to be confirmed, 3-week analysis period

The committee chooses option C, keeping the possibility of switching to B if the market analysis is unfavourable. This decision is recorded: it is a direct application of the triple constraint, documented before signature.

4. Test the assumptions. The "no new influx" assumption is judged moderately likely. Rather than writing it down and hoping, the design includes a 15% capacity margin in sizing the water points and a crisis modifier negotiated with the donor (a reserve of 5% of the budget that can be released with written agreement in the event of an influx of more than 3,000 people). The assumption "access to site C in the rainy season" is false two months a year: works on site C are therefore scheduled as a priority from February to June.

The completed charter (extract)

HeadingContent
TitleEmergency access to water, sanitation and hygiene for displaced and host populations in Kalema district
Duration12 months, from 1 February to 31 January
Target population18,000 IDPs and 4,000 host community members living near the water points, i.e. 22,000 people, of whom 52% are women and girls and 19% children under 5
Specific objectiveTargeted households have safe and dignified access to at least 15 L of drinking water per person per day, to latrines at a 1:20 ratio and to the means to practise handwashing
Deliverables20 functional water points with trained committees; 600 latrines; 3,600 households supported through cash transfers for hygiene; hygiene promotion campaign; operational complaints mechanism
ExclusionsShowers, solid waste management (covered by another NGO), urban piped water network
MilestonesBaseline survey end of February; contracts awarded mid-April; site C works completed end of June; interim report end of July; all facilities handed over end of November; endline survey December; closure January
BudgetEUR 1,205,000 including 7% indirect costs; AMD partner share: EUR 186,000
Main constraintsRainy season July-August, 10 to 12-week import lead time for pumps, partner's financial capacity
GovernanceMonthly steering committee chaired by the programme coordinator; internal change requests approved by the committee, any contractual amendment by the country director

The stakeholder matrix for the case

Low interestHigh interest
High influenceTerritorial administrator (keep satisfied: courtesy visit, invitation to handover ceremonies); immigration and customs services (keep satisfied: exemption files submitted early)Donor; water department; customary chief of Kalema (owner of the land for sites A and C); WASH Cluster
Low influenceUnsuccessful materials traders (monitor)IDPs in the three sites; host community; female heads of household; persons with disabilities; AMD

The analysis reveals a critical point: the customary chief controls access to land. Without written agreement for the 8 new boreholes, the project is blocked. Securing land agreements becomes a first-month task, with a named owner, and a risk is entered in the register.

9Common mistakes, the donor's perspective and variations by context

The costliest scoping mistakes

MistakeObserved consequenceHow to avoid it
Copying the logframe of a previous projectUnsuitable indicators, unrealistic targets, no baseline valuesStart again from the local problem tree; baseline survey before the first report
Not reading the agreementNon-compliant procurement, expenditure before the start date, visibility forgottenWalk-through of the agreement by finance at the kick-off
Targets not sized against standardsBeneficiaries "reached" with no real change in their conditionsCalculate gaps against Sphere and cluster standards
No explicit exclusionsPressure to add unbudgeted activities"Out of scope" section in the charter, communicated to authorities and communities
Partner brought in after the designPartner acting as a mere implementer without buy-in, underestimated running budgetsCo-design, partner budget built with them, partner indirect costs covered
Complaints mechanism planned "for later"First distributions without a complaints channel; abuse risks go undetectedMechanism operational before the first activity with communities
Unrealistic assumptionsLogframe invalidated by the third monthTurn critical assumptions into activities or managed risks

What donors, evaluators and auditors look at

  • When appraising the proposal: justification with recent, disaggregated data, consistency with the response plan, coordination with the cluster, cost per beneficiary and unit costs compared with benchmarks, risk and access analysis, partner capacity, mainstreaming of protection, gender and accountability.
  • Evaluators generally apply the OECD DAC criteria (relevance, coherence, effectiveness, efficiency, impact, sustainability), supplemented by those of the ALNAP guide for humanitarian action (coverage, connectedness). Relevance is judged on the quality of the scoping: were the priority needs identified with the populations?
  • Auditors check that what was funded matches what was contracted, that expenditure falls within the eligibility period, that procurement procedures were followed and that change decisions are documented. A well-kept charter and steering committee minutes are valuable supporting documents.

Variations by context

ContextWhat changes in scoping
Sudden-onset crisis (disaster, mass influx)Scoping in 72 hours to two weeks; secondary data and rapid assessment; light charter approved in one day; scope revised at 4 to 6 weeks as data become more precise. Donors' rapid response tools (emergency allocations, reserve funds) have short durations, often 3 to 6 months.
Protracted crisisFiner analysis, sustainability and handover from the scoping stage, linkage with state services and development (nexus), multi-year funding where available.
Camp or siteCoordination with site management (CCCM), limited space, site planning, Sphere ratios directly measurable.
Urban settingDispersed populations, difficult targeting, central role of municipal services and private operators, frequent use of cash transfers, interventions on networks rather than on stand-alone facilities.
Remote managementScoping with a partner or local staff, remote assessment (telephone, imagery), scope limited to what can be verified, third-party monitoring budget from the design stage.
High insecurityAccess and security analysis upstream, scenarios, scope adapted to actual access, realistic security budget, duty of care towards staff and partner.
Local partner with limited capacityOrganisational capacity assessment before contracting, budgeted capacity-strengthening plan, payments in instalments, explicit risk sharing rather than wholesale risk transfer.

The more unstable the context, the more the charter must explicitly provide for its own adaptation mechanisms: scenarios, crisis modifier, trigger thresholds and decision-making authority.

10Interview questions and key references

Interview questions

Recruiters for project manager or coordinator positions test the ability to reason through real situations, not the recitation of definitions. Here are frequent questions and what a strong answer contains.

  1. "You join a project that has already been signed. What do you do in your first two weeks?" A good answer mentions reading the agreement and its annexes, the budget and the logframe; meeting the team, the support services and the partner; a visit to the field and to the communities; checking imminent milestones (reports, major procurement); updating the risk register; organising or resuming the kick-off meeting.
  2. "How do you justify a project's target?" The answer links the target to the gap against standards (Sphere, cluster), to coverage by other actors (5W), to the budget and to access, and mentions baseline data.
  3. "The budget awarded is 20% lower than what you requested. What do you do?" The expected answer applies the triple constraint: costed options (reduction in scope, area or duration, change of modality), impact on standards and on populations, consultation with the cluster to avoid gaps, a formalised and communicated decision. Never keep the same scope while silently degrading quality.
  4. "How do you involve communities in scoping a project in an emergency?" Focus group discussions separated by sex and age, diverse key informants, information on the project and its limits, a complaints mechanism from the outset, feedback to communities on the choices made. Reference to the CHS.
  5. "What is a killer assumption and what do you do if you identify one?" Definition, a concrete example and, above all, the decision: revise the design or do not launch the project in that form.
  6. "How do you work with a local partner that has little experience with institutional donors?" Capacity assessment, co-design, a budget covering its real costs, a capacity-strengthening plan, instalments and financial support, fair risk sharing; reference to localisation commitments.

Key references

  • Sphere Project, The Sphere Handbook: Humanitarian Charter and Minimum Standards in Humanitarian Response, 2018 edition.
  • CHS Alliance, Groupe URD and the Sphere Project, Core Humanitarian Standard on Quality and Accountability (CHS), revised version 2024.
  • PM4NGOs, A Guide to the PMD Pro: Project Management for Development Professionals.
  • IASC, Joint Intersectoral Analysis Framework (JIAF) and Humanitarian Programme Cycle (HPC) guidance.
  • IASC, Multi-Cluster/Sector Initial Rapid Assessment (MIRA), guidance.
  • IASC, Six Core Principles Relating to Sexual Exploitation and Abuse and Commitments on Accountability to Affected People.
  • ALNAP, Evaluation of Humanitarian Action Guide.
  • OECD DAC, Better Criteria for Better Evaluation: Revised Evaluation Criteria Definitions and Principles for Use (2019).
  • CDA Collaborative Learning Projects, Do No Harm (analytical framework).
  • Washington Group on Disability Statistics, Short Set on Functioning.
  • European Commission, general conditions and guidelines applicable to humanitarian aid actions funded by the European Union.
  • United States Government, 2 CFR 200 — Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards.

Key takeaways from this in-depth day: solid scoping can be recognised by three things. The target is sized against standards and against other actors. The triple constraint trade-offs are written down and approved. Communities, the partner and the support services have been involved before the first purchase.

Scenario

Launching a project after floods

Flooded delta, South Asia

Your role

You are appointed project manager of a 6-month shelter and water response after floods.

The funding has been granted. Your team is not complete, the local authority wants to be consulted and three NGOs are already working in the area.

  1. Decision 1 of 3First action?

  2. Decision 2 of 3How do you deal with the three other NGOs?

  3. Decision 3 of 3The local authority asks for a school to be added for rehabilitation. The budget is fixed. What do you reply?

Exercise: a project charter

Take a real or imaginary project (for example a distribution of hygiene kits for 2,000 displaced households). Write on one page: the objective, three deliverables, the duration, the overall budget, five stakeholders placed in the influence / interest matrix, and three assumptions on which success depends.

Key points

  • A project is temporary and produces a unique result.
  • Phases: identification and definition, set-up, planning, implementation, closure; monitoring and control is continuous.
  • Scope, schedule and cost are linked: changing one moves the others.
  • The influence / interest matrix guides the relationship with each stakeholder.

💼 Programme management jobs

Put this course into practice: the latest jobs in this field.

See all 1126 Programme management jobs →

Prepare for the written test and interviewA model written test in this field, interview questions with sample answers and the STAR method.See the model test →
Further reading: course references
  1. PM4NGOs (2020). A Guide to the PMD Pro: Project Management for Development Professionals. www.pm4ngos.org
  2. European Commission (2004). Project Cycle Management Guidelines. international-partnerships.ec.europa.eu
  3. CHS Alliance, Groupe URD, Sphere (2024). Core Humanitarian Standard on Quality and Accountability (CHS). www.corehumanitarianstandard.org
  4. ALNAP (2022). The State of the Humanitarian System (report). www.alnap.org

Daily quiz

3 questions to check what you have learned. Answer them all to complete the day.

1What distinguishes a project from routine work?
2A stakeholder with high influence and high interest should be:
3If deliverables are added without changing the budget, you generally need: